Proposed Trail Build Dates - march to November 2018
« on: March 01, 2018, 02:07:37 PM »
Proposed Trail Build Dates - March to November 2018
Please note that build trails, dates and times may change depending on personal circumstances.
If there's a Parks Connect registration page, the build is going ahead unless further notified.
More info about each build is posted up two weeks or more before the build (hopefully).

MARCH
Saturday 24th - Upper Blair Witch Works

APRIL
Sunday 22nd - Redgum Realignment

MAY
TBC - Lower Buckle Features Rebuild
Please note: if we think we'll need two days to complete these tasks, we'll also have a build on Saturday before the Sunday

JUNE
Saturday 2nd - Lower Blair Witch Realignment
Please note: if we think we'll need two days to complete these tasks, we'll also have a build on Sunday 3rd

JULY
No build set, however if one does happen it will be on Saturday 28th

AUGUST
Sunday 19th - Adhoc work/drainage

SEPTEMBER
Saturday 15th

OCTOBER
Sunday 14th

NOVEMBER
Saturday 17th


Cheers.
« Last Edit: March 09, 2018, 01:59:04 PM by Nate »
LDTR Social Media & Head Trail Builder

Offline Nate

  • LDTR Committee
  • Hero Member
  • *
  • Posts: 837
  • Karma: 65535
Re: Proposed Trail Build Dates - march to November 2018
« Reply #1 on: March 09, 2018, 01:58:35 PM »
Please note that the May Trail build date will change.

Cheers,
Nate.

Sent from my SM-G930F using Tapatalk

LDTR Social Media & Head Trail Builder

Offline Nate

  • LDTR Committee
  • Hero Member
  • *
  • Posts: 837
  • Karma: 65535
Re: Proposed Trail Build Dates - march to November 2018
« Reply #2 on: March 14, 2018, 09:48:37 AM »
You might be wondering why our builds aren't starting at 8am like they regularly did in the past.
This is because we're making use of some funding between now and the end of the financial year. Thus, we're hiring machinery for the builds between this period. Most of the time the machinery will be being delivered on the Saturday morning. So we'll be waiting for the machines early Saturday mornings or using them to prepare materials for the build later in the day.

As always, you're free to attend a build or leave when you need to (just let the coordinator know).

Cheers,
Nate.
LDTR Social Media & Head Trail Builder

Offline CKaos

  • Full Member
  • ***
  • Posts: 171
  • Karma: 2
Re: Proposed Trail Build Dates - march to November 2018
« Reply #3 on: March 19, 2018, 11:43:10 AM »
Hey Nate,

The Redgum Realignment sounds interesting. What are the plans there?

Are we up for a round of the VES this year? If so, is one of these a pre race prep day on the trails?

Cheers, CK

Offline Nate

  • LDTR Committee
  • Hero Member
  • *
  • Posts: 837
  • Karma: 65535
Re: Proposed Trail Build Dates - march to November 2018
« Reply #4 on: March 20, 2018, 07:25:18 PM »
Hey Nate,

The Redgum Realignment sounds interesting. What are the plans there?

Are we up for a round of the VES this year? If so, is one of these a pre race prep day on the trails?

Cheers, CK
Hey Craig,
You'll have to attend to find out! haha nah, we're just realigning the section near comm games as per the audit. Nothing too big or crazy.

Haven't had any mention of a pre race build. Have a had a large amount of continuous work lately with other tasks for builds, but if one is required we'll try to pencil one in. It isn't a priority until we know tracks being used and the conditions later to the date.

Cheers,
Nate

Sent from my SM-G930F using Tapatalk

LDTR Social Media & Head Trail Builder